Aqua’s Pacifico study models only 23 LUEs and no fire flow

The 12-page packet for Resolution 26.08.02 says Aqua has sufficient capacity to serve a data center, but the attached engineering analysis tests a developer-supplied request of 9 gpm maximum-day demand, 14 gpm peak-hour demand, and no fire flow. Service is contingent on specified infrastructure. The packet does not establish total campus water demand, cooling design, fire-water supply, annual volume, final customer identity, or the enforceable terms of the future Non-Standard Service Agreement.