What Aqua’s Pacifico feasibility study actually proves
Aqua tabled proposed Resolution 26.08.02 on August 4, then placed the request on its September 1 agenda for discussion and possible action under Resolution 26.09.01. The new resolution and proposed agreement are not publicly available. The engineering report still answers only whether a future system can deliver a 23-LUE request with a 14-gpm peak and no fire flow—not the full campus water need.
Pacifico says its earlier project figures are out of date. Aqua should verify that its study still applies.
Pacifico's August 14 TCEQ application lists 48 gas turbines and states 1,326 MW of total maximum nominal electrical output. It does not mention the Organic Rankine Cycle equipment listed in the June JETI application and shown on a May conceptual plan released through Aqua. In a response relayed by State Rep. Stan Gerdes's chief of staff, Pacifico said its JETI figures are “out of date” and described approximately 1,100 MW of total nameplate generation and approximately 770 MW delivered to the customer. The underlying email reviewed by Lost Pines Watch is not presently published.
Those electrical figures measure different things and do not, by themselves, prove that Pacifico's Aqua water demand increased. Aqua's June feasibility study predates the new air application and modeled developer-supplied inputs of 23 living-unit equivalents, 9 gallons per minute of maximum-day demand, 14 gallons per minute of peak-hour demand, and no requested fire flow.
Before acting on Item 6, Aqua should require one current project description that reconciles those measures and a public written determination from its engineer explaining whether any changes to Pacifico's land uses, phases, equipment, construction needs, cooling design, or fire-protection plans affect the developer-supplied demand inputs modeled in June. If changes are needed, Aqua's June 26 transmittal says a new study is required at the developer's expense.
Table Item 6 until Pacifico supplies a current, reconciled project description; Aqua publishes Resolution 26.09.01 and the proposed agreement; and Aqua's engineer publicly determines whether the June study's modeled inputs remain valid.
This is not a total water-feasibility study for the campus.
It is a conditional hydraulic and capacity review of one narrowly defined Aqua connection. The report supports a finding that the modeled system—after completion of specified infrastructure—can convey the requested 14-gpm peak at adequate pressure.
It does not establish the total water demand of the now-filed 48-turbine, 1,326 MW generation proposal and associated data center, or show how cooling, fire protection, construction, wastewater, landscaping, and drought operations will be supplied. Pacifico now says its earlier JETI figures are out of date and has supplied different capacity measures, but the released records reviewed still do not reconcile them with the air application.
A 23-LUE request for a 2,841-acre power plant + data center development
Aqua’s packet lists 23 “LUEs Requested,” and the model says the anticipated demands were “provided by the developer.” In other words, 23 LUEs is the input Aqua tested—not an independently calculated estimate of the full development’s need.
The proposed approach main can carry the requested flow.
The model reports 53 psi at peak hour and low velocity after adding a 13,340-foot, 8-inch approach main. Aqua plans to upsize that line to 12 inches through existing CIP project NU-3. Construction and easement costs remain listed as TBD.
Eight issues Aqua should resolve before it acts
The realistic objective is not to claim that low-water technology is impossible or that Pacifico caused Aqua’s preexisting capital program. It is to make the public finding no broader than the evidence—and make the eventual limits enforceable.
The public application record is not auditable.
Aqua’s Water Service Tariff—its governing rules for water-service applications—requires a signed and sealed map or plat, detailed land uses, full-buildout average and peak demand for each land use, a buildout and demand schedule, fire-flow information, a project calendar, and on-site storage information. Aqua’s 12-page public packet omits the application exhibits, while the more detailed open-record production adds a conceptual plan but still does not supply a complete full-buildout water balance or final engineering package.
Identify and publish every item submitted under Water Service Tariff §6.16—or table the request if required material was not supplied.
The proposed resolution says more than the study establishes.
The resolution says Aqua has sufficient capacity to provide water service “to the data center.” The model tests a specific potable request: 23 LUEs, 9 gpm maximum day, 14 gpm peak hour, and no fire flow. It does not test the total water needs of the data center and power campus.
Limit the finding to the exact flow request and state expressly that total campus water feasibility was not evaluated.
Twenty-three LUEs is a developer-supplied input—not an independently derived need.
The report lists 23 “LUEs Requested” and says anticipated water demands were provided by the developer. Aqua’s study tests whether its system can serve that figure; it does not derive or validate the figure from a campus water balance. A low-water design can be real, but the packet contains no cooling design, annual demand, separate source plan, or binding operating conditions showing how the now-filed 48-turbine, 1,326 MW generation proposal stays within 14 gpm. Pacifico now says its earlier JETI figures are out of date and has supplied different capacity measures, but the released records reviewed still do not reconcile them with the air application.
Require a full-campus, all-source water balance tied to enforceable design assumptions and phase-by-phase limits.
The released records use different entity names and roles that require reconciliation.
The Aqua packet uses Pacifico Energy Development LLC and names Nayanika Dipak Panickar individually as “Developer.” The JETI applicant is Pacifico Cedar Creek LLC. The TCEQ application principally identifies Pacifico CCK Energy 1 LLC as the applicant but elsewhere uses Pacifico Cedar Creek LLC while describing the proposed facility. The JETI supplement says an unrelated third party will own and operate the data center, and BlackChamber appears on the data-center construction record. The released records reviewed do not explain how all of these names and roles relate.
Establish the member, landowner, meter tract, end users, assignment rights, and correct large-volume service classification before approval.
The unseen NSSA will contain the terms that make the number real—or meaningless.
Aqua’s governing service rules give the Board responsibility for approving water-service agreements and the general manager responsibility for negotiating and executing them. Resolution 26.08.02 would authorize negotiation and execution of the final Non-Standard Service Agreement without showing the Board or public its material terms.
Require the completed NSSA to return for Board approval at a posted meeting before it is executed.
The copy reviewed does not show a compliant engineering release.
The Garver memorandum displays a typed PE name and date, but no visible engineer’s seal or signature and no Texas engineering-firm registration number. Aqua may possess a compliant original; the packet reviewed here does not show it.
Publish the signed, sealed, dated final report with the registered firm name and number before relying on it.
The future-capacity scenario contains a large undisclosed commitment block.
The Nuse Zone grows from 697 existing connections to 1,532 connections before Pacifico is added—835 previously committed LUEs that are not identified. The model then adds only 16 LUEs of projected growth before adding Pacifico’s 23.
Publish the committed-development schedule, modeling horizon, capacity assumptions, and any TCEQ-approved alternative criteria.
Fire, construction, wastewater, and drought remain outside the analysis.
“Fire Flow Request: None” is not a fire-water plan. The study also does not address initial tank filling, emergency replenishment, construction water, dust control, landscaping, wastewater, drought curtailment, or the interaction with any on-site well.
Make service conditional on source-specific fire, construction, wastewater, cross-connection, and drought plans.
Aqua’s service rules require the inputs needed to test the 23-LUE claim
Section 6.16 of Aqua’s Water Service Tariff—its rulebook for water-service applications—says a large-volume, commercial, or industrial applicant must submit the following. The public packet does not show most of it. Those records may exist elsewhere in Aqua’s files; the Board should identify and publish them before acting.
- Completed feasibility-study request
- Signed and sealed map or plat
- Detailed intended land uses
- Estimated LUEs
- Full-buildout average and peak demand by land use
- Buildout and water-demand schedule
- Fire-flow quantity and duration, if requested
- Design, plat, construction, phasing, and occupancy calendar
- On-site storage and pressurization information
Twenty-three LUEs is an extraordinary outlier—not proof of impossibility
Water demand varies by orders of magnitude depending on cooling technology and operating rules. That makes the missing design assumptions more important, not less.
| Project or benchmark | Published water figure | What it shows |
|---|---|---|
| Pacifico / Aqua | 23 LUEs · 14-gpm peak hour | Developer-supplied demand; cooling design and annual volume not disclosed. |
| EdgeConneX / Aqua | 350 LUEs · 210-gpm maximum | The published figures differ by a factor of fifteen, but they measure different demand concepts. The campus covered by Aqua’s agreement is a roughly 130-acre, data-center-only project; Pacifico combines a data center and a 48-turbine power proposal whose air application states 1,326 MW of maximum nominal output across 2,841 acres. |
| Sabey / Round Rock | ≈3.8-gpm annual average (2.0M gallons/year) | Very low use is possible; Round Rock also makes closed-loop cooling and no continuous cooling-water draw binding requirements. |
| El Paso full buildout | ≈1,042-gpm average · ≈1,736-gpm maximum day | A different hyperscale design can require orders of magnitude more water. |
The figures are normalized to gallons per minute for scale, but they are not identical demand measures: Pacifico is peak hour, EdgeConneX is maximum flow, Sabey is observed annual average, and El Paso reports average-day and maximum-day allocations.
Even the peak-flow ceiling implies extremely low site water use.
If the entire 14-gpm peak were consumed continuously all year, it would equal about 7.36 million gallons. Using the earlier JETI figure of approximately 490 MW of IT load as a conservative benchmark—and assigning every drop to that load operating continuously—produces an implied site WUE of about 0.0065 liters per kWh.
LBNL reports a U.S. data-center average just above 0.36 L/kWh and published hyperscale values of 0.1–0.3 L/kWh for some low-water airside-economizer and adiabatic systems. Pacifico’s implied ceiling is roughly 15–55 times lower than those reference points.
LBNL 2024 data-center reportLow water is technologically plausible.
Pacifico’s JETI filing identifies air-cooled / fin-fan equipment for the generation plant. Air-cooled data-center systems can also use little or no cooling water, usually with an energy tradeoff.
The defensible conclusion is therefore not that 23 LUEs must be false. It is that Aqua has not published the design or binding conditions that make the number credible for this project.
A full-campus water balance should reconcile every use and every source.
The study can be adequate for a 14-gpm connection only if the public record shows what that connection serves, what it does not serve, and where all excluded water comes from.
- Data-center cooling and humidification
- Power-plant cooling and auxiliary uses
- Turbine washing, inlet cooling, fogging, and emissions-control water
- Initial equipment and fire-tank filling
- Fire suppression and emergency replenishment
- Sanitary demand and wastewater generation
- Construction workforce, concrete work, and dust control
- Landscaping and long-term site maintenance
- Every Aqua, groundwater, trucked, reused, and nonpotable source
- Average, maximum-day, peak-hour, and annual demand by phase
The final NSSA should return to the Board in public
No clear rule requires a completed NSSA before an initial feasibility decision. But Aqua’s governing service rules say the Board approves water-service agreements, while the general manager negotiates and executes them. The final contract is where the 14-gpm claim must become enforceable.
Valid for 90 days—through approximately September 24, 2026.
Resolution 26.08.02 is not approved; its signature lines remain blank.
Item 6 lists discussion and possible action on Resolution 26.09.01; the resolution and proposed agreement are not publicly available.
The NSSA should contain, at minimum:
- A hard 9-gpm maximum-day and 14-gpm peak-hour limit
- Daily, monthly, and annual volumetric ceilings
- Automated metering and an enforceable flow restriction
- An express list of which uses may—and may not—draw Aqua water
- No increase without a new feasibility study and Board vote
- No assignment to a tenant, affiliate, purchaser, or successor without Board approval
- Identification of every other source and cross-connection protection
- Binding drought curtailment without preferred industrial status
- Developer payment and financial security for dedicated facilities and easements
- Public reporting of aggregate monthly consumption
Who receives the water, what protects the site, and what is the final engineering record?
One meter cannot obscure multiple owners or uses.
Aqua’s study lists six appraisal accounts. Pacifico’s JETI filing lists eight, adding parcel IDs 90755 and 92335. If Aqua intends to use Single Owner Large Volume Service, its tariff limits that class to facilities on one tract owned by one person or entity and bars water purchased for resale.
Aqua should identify the landowner, member, meter location, power facility, data-center end user, and any transfer or submetering arrangement before it decides eligibility.
“No fire flow requested” does not answer the fire-water question.
A project-owned tank or separate source may be entirely appropriate. The packet simply does not disclose tank capacity, initial filling, refill rate, pump and hydrant design, emergency replenishment, or fire-authority approval.
The same gap applies to the projected peak construction workforce, dust control, potable water, and wastewater handling.
The Board should rely on a visibly final professional document.
Texas engineering guidance says released reports must be signed, sealed, and dated, and must identify the registered engineering firm and firm number. The reviewed copy does not display those elements.
That is a request for the proper final copy—not a claim that no such copy exists.
Texas engineering-board guidancePublish the record, narrow the finding, and bind the limits.
Aqua can evaluate an eligible customer’s connection without declaring that it has established the water feasibility of an entire data center and power campus. Before any future action, it should publish:
- The complete §6.16 feasibility request and every attachment.
- A PE-certified, all-source water balance and the engineering basis for 23 LUEs.
- The fire-water source, storage, refill rate, and authority-having-jurisdiction approval.
- A signed and sealed final feasibility report with the firm registration number.
- The draft and final NSSA, with enforceable flow and volume limits.
- The 835 previously committed Nuse Zone LUEs and the model’s growth horizon.
- An itemized estimate for project-specific construction, easement, and meter costs.
- Any TCEQ-approved alternative capacity criteria relied upon in the engineering analysis.
- The exact customer, owner, meter location, parcel scope, end users, and assignment rights.
- Construction, wastewater, drought, groundwater, and cross-connection plans.
Replace the campus-wide claim with the connection Aqua actually studied.
Aqua’s engineers determined only that, following completion of the identified improvements and satisfaction of all regulatory conditions, Aqua may be able to provide a potable-water connection capped at 9 gpm maximum-day and 14 gpm peak-hour demand. The determination excludes fire flow and does not establish the total water requirements or overall feasibility of the proposed data center or power-generation facility.