Independent public-interest researchEvidence verified through July 26, 2026
Resident action center

Ask for a pause, stronger rules, and a better site.

The immediate county decision is not whether every disputed impact is already proven. It is whether Bastrop County should adopt weak rules or subsidize a 710 MW project before the full-buildout record and site suitability can be publicly tested.

Monday, July 27, 2026

Be in the room before 9:30 a.m.

Bastrop County Commissioners Court Room, 2nd Floor
804 Pecan Street, Bastrop, Texas

The regular meeting begins at 9:00 a.m. The official agenda sets the tax-abatement-guidelines hearing for 9:30 a.m. Give the County Clerk a completed participation form before the item is discussed. Mark the relevant agenda item and whether you are for or against it.

Draft policy review

The July 27 draft is a start—not an adequate guardrail

This review credits the safeguards the draft actually contains and identifies the provisions residents can ask the court to strengthen.

Read the official draft
Useful provisions

Keep and make enforceable

  • Environmental information covering water, stormwater, floodplains, wetlands, waste, noise, and air.
  • A 25% Bastrop County business-participation target for construction, supplies, and services.
  • A 25% county-resident target for new full-time jobs.
  • Annual compliance reporting, recapture provisions, a ten-year continued-operation requirement, and wind-down or cleanup security.
  • Authority to require an applicant-funded professional feasibility review.
Material gaps

Fix before adoption

  • Environmental disclosure is undefined and qualified by “to the extent practical and applicable”; no required methods, baselines, modeling, or independent certification.
  • No full-buildout or cumulative-impact rule covering affiliates, co-located generation, data centers, backup generators, pipelines, substations, or shared water demand.
  • No required online publication date, minimum public-review period, or mandatory hearing before the final abatement agreement.
  • A majority may grant variances, while the “extraordinary economic benefit” needed for a 100% abatement is not defined.
  • The 25-job threshold matches Pacifico’s projection despite a revised $2.237 billion investment and 710 MW facility; there is no benefits-per-job test.
  • No alternative-site analysis, residential or school buffer, drought test, emergency-capacity standard, or binding denial criterion for an incompatible site.
Requested amendments

Eight concrete asks for Commissioners Court

Residents can support stronger standards without conceding that Pacifico is suitable for this location.

01

Pause discretionary abatements

Do not approve new data-center or co-located generation abatements until sector-specific standards and cumulative-impact rules are adopted.

02

Require one full-buildout disclosure

Aggregate every phase, affiliate, host parcel, turbine, backup generator, data hall, substation, pipeline, water source, and reasonably foreseeable expansion.

03

Quantify community burdens

Require water and power demand, ratepayer effects, air emissions, noise, traffic, drainage, fire-water, hazardous materials, evacuation, and drought consequences.

04

Make independent review mandatory

Use applicant-funded experts selected by the county, publish their work, and require written resolution of material deficiencies before a hearing.

05

Guarantee public review

Post the full application and technical record online, allow at least 30 days for review, and require a hearing before every final agreement.

06

Add a site-suitability test

Require residential and school proximity, emergency capacity, water, road, wildfire, and alternative-site findings—and deny abatements where the site is incompatible.

07

Close exception language

Replace “to the extent practical” with defined minimums and require public written findings for any variance.

08

Define public value

Define “extraordinary economic benefit,” publish a benefits-per-job analysis, and prohibit a 100% abatement on vague or confidential assertions.

A focused public-comment outline

Use your own words, but cover these four points

  1. Who you are: your name and that you live, work, farm, attend school, or serve the community in Bastrop County.
  2. Your position: do not adopt the draft as written and do not approve a Pacifico abatement at this location.
  3. Your evidence: 710 MW and only 25 projected permanent jobs; 854 anonymous residential sites within one mile; or the missing fire, water, air, and cumulative-impact record.
  4. Your ask: pause abatements, adopt the amendments, require an alternative-site analysis, and direct Pacifico to seek a more suitable industrial location.
Community proposal

The proposed Bastrop Bill of Rights

Elgin attorney Nick Lealos proposed this five-part agenda at the July 22 town hall. It is a community proposal—not adopted county law.

Credit: Nick Lealos

The Observatory credits Lealos as the proposal’s author. We located a durable professional identity record and a link to the full-town-hall recording, but not a standalone document published by Lealos containing the complete text.

  1. 1

    Require tax-abatement applicants to disclose projected water and electricity demand and effects on cost and availability.

  2. 2

    Publish applications and supporting documents online.

  3. 3

    Establish a citizen advisory committee.

  4. 4

    Pause new data-center abatements while standards are developed.

  5. 5

    Ask state leaders for a special legislative session and greater county regulatory authority.

Petitions and campaigns

Add your name, then take a record-making action

Petitions demonstrate organized public concern. They do not replace comments filed in a permit proceeding, a county participation form, an email to a decision-maker, or testimony at a public meeting.

Bastrop County

No AI Data Center in Bastrop County!

A local petition directed to the Bastrop County judge and commissioners. It began before Pacifico’s proposal became public and addresses additional data-center development countywide, so it should not be described as Pacifico-specific.

2,276 verified signatures shown July 26, 2026Open the local petition
Texas

Put People Over Data Centers in Texas

A statewide pledge sponsored by Ground Game Texas calling for transparency, accountability, protection of land, water and power, and opposition to unchecked data-center expansion.

Statewide campaign · not project-specificOpen the statewide petition
No Pacifico-only or verified paper petition located yet.

The widely circulated tinyurl.com/nobastropai link is publicly indexed with the countywide Change.org campaign above. We use the direct destination instead of the shortened link. If a Pacifico-specific or offline petition exists, send us the organizer, wording, recipient and signing instructions so it can be verified and added.

Submit a petition or campaign
Community discussion

Where residents are comparing notes

These channels are useful for organizing and discovering leads. Social posts are not automatically treated as verified evidence by the Observatory.

Nextdoor · Cedar Creek

Current Pacifico and data-center discussion is visible in Cedar Creek neighborhood feeds. Nextdoor may require an account and neighborhood verification; treat posts as leads until their claims are checked against records.

Open Cedar Creek on Nextdoor

Living in Bastrop County

Residents are sharing meeting details, articles, petition links and local observations in this Facebook group. Group visibility and individual posts may require a Facebook account.

Open the Facebook group
Who to contact

Bastrop County Judge and Commissioners

Calling and emailing create a written record, but they do not replace the official participation form or any permit-specific filing instructions.

Permits and records

Use the right channel for the right decision

A general email may raise awareness. Formal permit comments, hearing requests, and public-information requests must follow the agency’s instructions.

State authority

Senator Charles Schwertner · Senate District 5

Bastrop County is in SD 5. Ask for the same local-control, disclosure, and cumulative-impact safeguards.

Capitol: 512-463-0105Official contact
Air-permit watch

Do not let a fragmented public record become a fragmented review

Statewide reporting documents projects that started with minor authorizations and later sought much larger fleets. That history is a reason to demand Pacifico’s full buildout—not proof Pacifico has already used the same approach.

Watch the public list

No Pacifico or Cedar Creek name match was located on TCEQ’s pending case-by-case and standard-permit posting on July 26. That is not proof that no application or authorization exists.

TCEQ pending applications

Ask the aggregation question

Request a written determination addressing every project phase, turbine, generator, affiliate, co-located operation, and shared industrial purpose.

EPA source-aggregation guidance

Preserve hearing rights

When a permit notice opens a comment period, raise specific air, modeling, receptor, and aggregation issues within that period and follow the notice’s hearing-request instructions.

TCEQ participation guide
Source note: The Texas Tribune / Floodlight article supplies the statewide investigation. EPA materials provide the federal permitting framework. The Observatory does not infer a Pacifico violation from another company’s conduct.Read the investigation
Records work

Current request queue

Statuses describe the Observatory’s working plan. They are not claims that an agency has received or answered a request.

REQ-001 · AirSubmitted by email · July 26, 2026

TCEQ

Full NSR application, supplements, correspondence, modeling, turbine data, stack parameters, and engineering drawings.

Next: Await and log the agency acknowledgment, tracking number, production schedule, and response milestones.
REQ-002 · Civil / siteDraft next

Bastrop County Development Services

Development, grading, drainage, OSSF, driveway, access, and right-of-way records identified in the JETI permit table.

Next: Prepare one request keyed to Pacifico, the address, and parcel variants.
REQ-003 · WaterDraft next

Groundwater district / Aqua WSC

Well, production, permit, and water-feasibility records associated with the site.

Next: Request records under applicant, address, and parcel variants.
REQ-004 · Traffic / right-of-wayDraft next

TxDOT

Encroachment, driveway, access design, utility crossing, and state right-of-way records.

Next: Identify district and project references.
REQ-005 · Fire / emergencyJurisdiction research

Fire jurisdiction / ESD

Fire-code review, water, hydrants, apparatus access, hazardous materials, staffing, mutual aid, and pre-incident planning.

Next: Resolve the primary responding jurisdiction before submission.
REQ-006 · JETI reviewDraft next

Texas Comptroller / Bastrop ISD

Non-confidential correspondence, deficiency notices, consultant questions, revised exhibits, and records concerning Supplement 1 and the compelling-factor determination.

Next: Prepare request keyed to J0049 and Pacifico Cedar Creek LLC.
REQ-007 · Alternative siteSource collection

Muhlenberg Township, Ohio

Zoning applications, minutes, recordings, moratorium ordinance, staff correspondence, and site-control records.

Next: Confirm exact effective and expiration dates and continuing site control.