The Cedar Creek story, with the source record attached.
This page gives reporters, researchers, civic groups, and public officials a clean starting point without flattening confirmed facts, estimates, leads, and unknowns into one claim.
Content reviewed October 28, 2026 · Evidence dates appear with the records.
What the public record currently supports
Numbers below are rounded for briefing use. Follow the source links before publication.
Last verified pending · October 1
Registration 185019 / Project 413471 was pending at the last verified project-tracker check on October 1, 2026. A fresh project-specific check could not be completed October 28; this is not confirmation of today’s disposition. The September 21 directive pauses data-center permit issuance pending ERCOT’s review. No Pacifico restart or decision date is established by the records reviewed.
Check TCEQ’s project recordRead the permitting-pause update
Approved September minutes are now public
Aqua’s posted, approved September 1 minutes record unanimous approval of Resolution 26.09.01 and the NSSA, with final negotiations on outstanding portions authorized. A final executed agreement has not been verified. Minutes checked October 28, 2026.
Read the study and current agreement questionsCoreWeave is the registered AUS02 occupant
The Texas Comptroller identifies CoreWeave as occupant of EdgeConneX AU02. Earlier reporting projected an August opening; Lost Pines Watch has not independently confirmed commercial operation as of October 1. This is separate from Pacifico.
Open the FM 535 corridor recordUse these distinctions in coverage
Lost Pines Watch takes a public position while keeping its evidence labels explicit.