The Cedar Creek story, with the source record attached.
This page gives reporters, researchers, civic groups, and public officials a clean starting point without flattening confirmed facts, estimates, leads, and unknowns into one claim.
What the public record currently supports
Numbers below are rounded for briefing use. Follow the source links before publication.
Registration 185019 entered a final-package cycle
TCEQ still listed the registration as pending on August 30. The released application identifies 48 turbines across six model families and states 1,326 MW of maximum nominal output. Final enforceable terms and TCEQ's written eligibility basis remain unresolved.
Open the current action update →Aqua schedules September 1 consideration of Pacifico
Item 6 schedules discussion and possible action on Large Volume Water Service through Resolution 26.09.01. The new resolution and proposed agreement are not publicly available. The existing study models only 23 LUEs, a 14-gpm peak and no fire flow—not a complete campus water balance.
Read the meeting action guide →CoreWeave is now officially named at AUS02
The Texas Comptroller lists CoreWeave as occupant of EdgeConneX AU02. Community Impact reports the $440 million building is expected to open in August. This is a separate project from Pacifico.
Open the FM 535 corridor record →Use these distinctions in coverage
Lost Pines Watch takes a public position while keeping its evidence labels explicit.