Independent public-interest researchEvidence verified through September 2, 2026

Governor Greg Abbott has directed the Texas Commission on Environmental Quality to “pause the issuance of all permits related to data center projects until ERCOT completes its review.” The September 21 letter changes the permitting outlook for Pacifico’s proposed Cedar Creek power plant. Read the directive.

Ben Watson of Rep. Stan Gerdes’s office said, in correspondence shared with Lost Pines Watch, that the Governor’s office intended Pacifico to be covered “without exception.” Gerdes publicly described discussing Pacifico with the Governor’s team on September 21.

According to a local resident’s notes from a September 22 call, Sam Short, Deputy Director of TCEQ’s Air Permits Division, confirmed that Pacifico was covered by the pause and its application was not moving forward. He also said it had reached him for final review. This account places Registration 185019, Project 413471 at an advanced review stage when the pause intervened. TCEQ identifies Short’s role here.

The dates to watch

2026 unless noted

  1. September 21

    The Governor directs TCEQ to pause permit issuance for data center projects. This is the new instruction affecting the permitting process. Governor’s announcement.

  2. September 22

    According to the caller’s notes, Sam Short confirms the pause applies to Pacifico and says the application had reached him for final review. No final eligibility determination had been made.

  3. October 5

    Civic reminder — Voter registration deadline in Texas for the November 3 election. Check your registration and find registration instructions at VoteTexas.gov.

  4. October 12

    Recipients of ERCOT’s State and Community Impact information request must respond by 5 p.m. Central. We have not confirmed whether Pacifico or its prospective data-center customer received it. ERCOT notice.

  5. October 14

    The Texas Water Development Board must report on progress enforcing water reporting requirements. This is a progress report, not a promised audit completion date. TWDB directive.

  6. October 19

    TCEQ must update the Governor on compliance with the directive. The date does not automatically authorize a permit or end the pause. TCEQ directive.

  7. December 10

    ERCOT expects to publish its State and Community Impact report by this date, in coordination with the PUCT. Its August schedule also targets this date for a separate report on eligibility for Batch Zero, ERCOT’s grouped review of large grid connections. Report notice · August schedule.

  8. December 17

    PUCT open meeting shown in ERCOT’s audit schedule. This is a statewide milestone; no Pacifico-specific decision or automatic permit restart is established. ERCOT schedule.

  9. January 12, 2027

    The next regular legislative session begins. New protections may be considered; neither their passage nor their application to Pacifico is settled. Legislative calendar.

What onsite power means for ERCOT review

Pacifico has described behind-the-meter generation to supply power onsite. That does not establish that the campus will have no grid connection. ERCOT says truly isolated facilities generally fall outside its interconnection process, although PUCT registration may still apply. ERCOT’s explanation.

The earlier filings show why the connection question remains open. The original state tax-incentive application described behind-the-meter generation and listed Bluebonnet Electric Cooperative interconnection equipment (pages 7 and 12). Supplement 2 again listed Bluebonnet Electric Cooperative interconnection equipment (page 4). These equipment lists document a contemplated utility connection. We have not confirmed whether that equipment remains in the current design, its intended purpose or capacity, or whether an interconnection agreement exists.

ERCOT’s information request expressly asks about onsite generators that can operate alongside the grid, even when they cannot export electricity. It also asks about grid demand, generation, water use and community impacts. Onsite generation therefore does not, by itself, establish that ERCOT’s review would be minimal. See the questions, especially B-2l–B-2n.

Our assessment: If Pacifico and the associated data center will operate entirely without a grid connection, ERCOT’s direct interconnection review could be limited or unnecessary. That condition has not been verified. A limited ERCOT role would not, by itself, release Pacifico from the TCEQ permitting pause; the directive contains no express behind-the-meter exemption.

What may happen next

The application had reached final review, but TCEQ had not made its final eligibility determination. The caller’s notes do not establish whether staff recommended approval, whether all deficiencies were resolved, or what work remained.

If TCEQ resumes the existing standard-permit review, a decision could follow relatively quickly. If Pacifico must revise its proposal or seek a different permit, additional technical review and applicable public-participation steps could substantially change the schedule. The remaining work and decision date are unknown. A motion to overturn an issued approval does not automatically suspend it.

The October agency reports and December ERCOT milestones are checkpoints. Neither October 19 nor December 10 or 17 automatically ends the pause. The December reports may clarify the statewide review, but their scheduled dates do not establish Pacifico’s individual review requirements or a permit decision date. The restart date remains unknown. The directive also does not expressly revoke existing authorizations or stop every activity at the site. Read the directive.

Beyond the air permit

The air permit is one milestone in a larger development process. A clearer project timeline also depends on updated information from Pacifico about remaining approvals, utility and infrastructure work, and construction and startup milestones. The proposal could proceed, change, move to another location or be withdrawn. Costs, regulatory requirements and commercial decisions can change a project’s plans. The pause alone does not tell us which outcome will occur or when.

The statewide data center audit

On August 3, Governor Abbott directed the Public Utility Commission of Texas (PUCT), the state utility regulator, and ERCOT, the grid operator for most of Texas, to audit data center projects seeking grid connections before allowing them to advance. His directive also requires information about power demand and generation, water and cooling, public financial assistance, ownership, and community protections, including noise controls, lighting, setbacks, traffic and emergency response. Read the Governor’s August 3 directive.

This statewide review can inform permit decisions. It does not itself establish specific protective setbacks or guarantee a public meeting. Its implications for the Pacifico project still need to be explained.

The answers residents need

For the Pacifico project, the immediate questions are concrete:

  • What work remained when Pacifico reached final review, and which application version and calculations are TCEQ reviewing?
  • Will Pacifico and its prospective data-center customer have any grid connection, including backup supply or electricity exports? Does the current design retain the Bluebonnet equipment? A current electrical connection diagram and utility confirmation would help answer this.
  • Has Pacifico or the data-center developer received an ERCOT information request, and which review requirements apply to the planned connection?
  • What must happen before review and permit issuance can resume, and who decides that those requirements have been met?
  • Will TCEQ provide advance notice and access to the supporting records before releasing the hold or making a permit decision?
  • Will TCEQ address a focused technical submission before acting, including the emissions calculations, operating limits and treatment of the power plant and data center?

The advanced review stage makes timely public access to the records and technical answers especially important. Any proposed protections must be specific and enforceable.

Clarifying Lost Pines Watch’s role and position

The September 22 Austin Business Journal article describes discussions between residents and the developers as negotiations. Because the article also identifies a participant’s connection to Lost Pines Watch, we want to clarify our organization’s position.

The developers selected this site and began planning the project (possibly as far back as 2.5 years ago) before seeking input from the wider community. That lack of early transparency has left Lost Pines Watch and local residents piecing together information from public records and direct questions to the companies. Seeking answers does not signal support for the project.

Some residents involved in these discussions also communicate directly with Lost Pines Watch. That communication does not authorize them to speak for the organization or make commitments on its behalf. Lost Pines Watch has not authorized anyone to offer its support for the project or negotiate an agreement on its behalf.

Our position remains unchanged: Lost Pines Watch opposes the proposed development at this location and seeks relocation of the proposed fossil-fuel generation or a redesign that eliminates it. By redesign, we mean evaluating alternatives such as solar and battery storage in place of the proposed gas-fired power plant. We continue to gather, verify and share information, scrutinize the project’s claims, and support informed community action.

We want to preserve our rural Texas neighborhoods and the homes, schools, farms and way of life already here. Governor Abbott has called on data center developers to put communities first, protect natural resources and respect residents’ quality of life. We share those priorities. Communities deserve meaningful involvement while siting and design choices are still open to change.

The permitting pause does not mean the project has been canceled, and discussions with developers do not establish community consent.

Stay informed
and take part

Lost Pines Watch is actively monitoring TCEQ’s public permit record for this project. Automatic decision notices are not provided by TCEQ for this registration. Residents can follow Lost Pines Watch’s updates without having to check the permit database themselves.

The Lost Pines Watch School Coalition has launched! Parents and staff at local schools and childcare organizations are invited to join. Sign up for the School Coalition, and share the link with other parents and staff in your school or childcare community.

You can sign up for local alerts, DONATE to support Lost Pines Watch’s research and community outreach, or join the community opposition map.

Source note: The caller’s notes from September 22, Watson correspondence and Gerdes’s September 21 post were shared with Lost Pines Watch. The notes describe an oral status update, not a written TCEQ determination. Linked public records support the dated milestones and equipment history. Possible timelines, project outcomes and the conditional ERCOT inference are Lost Pines Watch’s assessment; none is guaranteed.