Texas has resumed data center permits. Was Cedar Creek ever part of the state’s review?

The state’s grid operator surveyed data centers seeking grid connections. Pacifico says its Cedar Creek campus would generate its own electricity with 48 gas turbines on Earl Callahan Road.

On November 17, the Texas Commission on Environmental Quality (TCEQ) confirmed to The Texas Tribune that it had resumed reviewing data center permits. Gov. Greg Abbott’s office had notified TCEQ on November 13 that the state’s grid operator, ERCOT, had finished collecting information on potential community impacts.

ERCOT surveyed certain data centers seeking at least 25 megawatts of grid service. It asked about on-site power, water use, noise and traffic. Its November 5 briefing counted responses for 433 of the 465 electricity loads surveyed and gave December 10 as the target for its final report. The public figures leave Cedar Creek’s participation unclear. Did any state agency examine how Pacifico’s project would affect its neighbors before the pause ended? If so, will it share that assessment?

The Austin Business Journal reported in August that Anthropic was in talks to lease the campus. The state’s accessibility filing for Building One lists the tenant as “Not Assigned” and November 30 as the planned start for the data center building. Anthropic priced its initial public offering on November 18. It has pledged to address environmental impacts where partners develop data centers for its use. Will Anthropic meet Cedar Creek families and say whether it would support moving the proposed gas plant away from homes and Earth Native Wilderness School?

Read the reporting and records behind this update

Our open letter to Anthropic

On one signature sheet, a neighbor wrote “50 feet” for the distance from their home to the proposed site’s property line. Others wrote “8 miles” and “25 miles.” Our October 20 letter carries 73 handwritten signatures from across Bastrop County. We sent it to Anthropic by certified mail on November 19, the day its shares began trading.

Pacifico CCK Energy proposes to build a 48-turbine natural gas plant on Earl Callahan Road to power BlackChamber’s planned data center. Our letter notes that more than 850 homes sit within a mile of the site and about 25 schools and daycares sit within four miles.

On August 14, Anthropic committed to Gov. Greg Abbott’s data center standards. One of those commitments was to protect residential neighborhoods from disruption. Read the governor’s announcement.

What we’re asking Anthropic to do

  1. Publicly support a formal public hearing on the Pacifico gas plant permit before any decision is made.
  2. Meet publicly with Cedar Creek residents, including the farmers, business owners, schools and organizations closest to the site.
  3. Hold off on this site until the community understands the full impact of the project and has had a real say in its future.
View the four redacted pages

The handwritten distances are the signers’ own estimates. Open the original photographs.

Read the typed letter as text

An Open Letter to Anthropic

October 20, 2026

On August 14, 2026, Anthropic publicly committed to Governor Abbott’s data center standards, including that data centers “not disrupt residential neighborhoods to preserve Texas’ quality of life.” The Governor has also said companies must earn buy-in from the communities where they build.

We are residents of Bastrop County. County records and press reports identify Anthropic as the planned tenant of a data center in Cedar Creek, to be powered by a 48-turbine gas plant on Earl Callahan Road.

More than 850 homes sit within a mile of that site. About 25 schools and daycares sit within four miles.

There has been no buy-in. This project has moved forward for a long time without any formal public process.

The plant’s air permit was filed on a track that provides no public notice, no comment period, and no hearing. More than 200 residents have asked TCEQ for a public meeting. So have our elected officials: the Bastrop County Commissioners Court voted unanimously to request one, Rep. Stan Gerdes formally asked for one, and Sen. Charles Schwertner pressed TCEQ on how residents can be heard. None has been granted.

We ask Anthropic to honor its pledge:

  1. Publicly support a formal public hearing on the Pacifico gas plant permit before any decision is made.
  2. Meet with Cedar Creek residents, in public, including the farmers, business owners, schools, and organizations closest to the site.
  3. Do not proceed with this site until this community understands the full impact of the project and has had real input on its future.

You asked to be held to this standard. We’re holding you to it.

The typed October 20 letter and its three requests, followed by redacted signatures.
Page 1 · The open letter
Redacted signature sheet with handwritten distances including 50 feet, 2,000 feet and 25 miles.
Page 2 · Signers’ distances from the site
Redacted signature sheet with handwritten distances, including one, three, eight and ten miles.
Page 3 · Signers’ distances from the site
Redacted signature sheet listing communities including Bastrop, Cedar Creek and Elgin.
Page 4 · Signers’ communities and distances

What Anthropic told CBS Austin

On November 19, an Anthropic spokesperson told reporter Adela Uchida the company was in talks about the Cedar Creek data center and had not signed a lease. That leaves time for Anthropic to sit down with the families who would live beside the plant.

Uchida also spoke with neighbors about the noise and heat the project could bring and what it could mean for local wildlife. Lucy D. told her why the proposal weighs on her family.

“I’ve got a four-year-old and a one-year-old, and it keeps me up at night.”

Lucy D., speaking to CBS Austin
Watch the CBS Austin report

What Anthropic can agree to before signing a lease

Anthropic’s November 17 IPO filing explains that the company can owe developers money for equipment and materials ordered early, even if the parties never sign a lease or the developer cannot secure construction financing. As of September 30, the maximum it could owe across those agreements was $4.2 billion companywide. The filing identifies no Cedar Creek agreement. Read Note 13, page F-61.

Has Anthropic or an affiliate agreed to cover work at Cedar Creek, paid a deposit, or reserved equipment for this site? A commitment like that could come before the lease discussed in the CBS Austin report.

Some of Anthropic’s planned data centers would rely on dedicated gas plants. Anthropic says a project could stall if it cannot secure fuel and pipeline capacity. It also describes deals involving the operation or control of power stations. Pacifico told the Texas Comptroller that an unrelated company would own and operate any Cedar Creek data center and could buy some of the plant’s electricity.

We’d like Pacifico, BlackChamber and Anthropic to say who would own the 48 turbines, who could decide when they run, and who would buy their power. Anthropic’s power disclosures, pages 43–44 and 80 · Pacifico’s state filing, page 12.

Lost Pines Watch and UPROAR go to Washington

Cameron Allen of Quelite Farm & Food is an eighth-generation Texan and Lost Pines Watch volunteer who farms near the proposed plant. Before his flight from Austin on November 18, he recorded a message about his 11-year-old daughter and the families who would live with the project.

Uproar Movement organized the trip. Cameron represented Lost Pines Watch alongside participants from several sovereign Indigenous nations and residents of Philadelphia and Washington, D.C. People also came from Georgia, Michigan, Missouri, New Jersey, New Mexico, Oklahoma, South Dakota, Tennessee, Utah and West Virginia. Read Uproar Movement’s event announcement.

A group holds a banner reading “The People Say Stop the Data Center Giveaway” and “Stop BAAJA,” with the U.S. Capitol behind them.
Participants in UPROAR’s action gather outside the U.S. Capitol to oppose the federal permitting bill.

“We just want a company that made a promise to our neighborhoods to keep it, and to talk to us before it builds a gas plant next to our homes.”

Cameron Allen, in our November 19 press release

In his November 19 video, Cameron said he went to Washington to oppose Anthropic’s stock market debut and the Bipartisan American Affordability and Jobs Act of 2026 (BAAJA), a bill to speed up federal permitting for energy projects. He wanted to ask Sen. Ted Cruz about his support for fossil fuels. Cameron said he repeatedly asked for a meeting and told staff he would stay until he got one. He said Capitol Police arrested him and one other person outside Cruz’s office and released them about an hour later.

Cameron Allen takes a selfie beside a U.S. Capitol Police van.
Cameron in Washington on November 19, beside a U.S. Capitol Police van.
A teal-and-gold Lost Pines Watch pin on the lapel of Cameron’s jacket.
The Lost Pines Watch pin Cameron wore in Washington.

The bill now goes to the House

On November 19, the Senate voted 62–33 to pass BAAJA. Cruz voted yes. Sen. John Cornyn did not vote. Ask your U.S. representative to vote no on the Senate version of H.R. 2347.

Commissioners take up possible EdgeConneX tax abatements on Monday


Commissioners Courtroom, second floor, 804 Pecan Street, Bastrop

Precinct 1 Commissioner Butch Carmack placed possible county tax abatements for EdgeConneX and the company’s proposed community benefits on the Bastrop County Commissioners Court agenda. Section E, item DO3 is for discussion only.

EdgeConneX has data center projects near Elm Ridge. The county’s one-page report leaves the property, dollar amount, duration and proposed benefits unspecified. Which property would qualify? How much county tax would EdgeConneX save, for how long, and which promises to neighbors would the county put in writing and enforce?

To speak, list E / DO3 on the county’s public participation form and give it to the County Clerk before commissioners reach the item.

Ranch Revival benefit concert


Kintsugi Ranch, 359 FM 969, Bastrop, TX 78602

Join Lost Pines Watch for Keep It Country, a free concert to help Cedar Creek neighbors pay for legal representation as they challenge Pacifico’s proposed gas plant.

Pendulum Hearts, Candler Wilkinson IV and David Milner will play. The afternoon also includes dancing, a raffle and a cowboy chili cookoff. Kids are welcome.

Event details and RSVP
Keep It Country concert flier with a Texas flag and portraits of the three performers.Download the event flier (JPG)