Independent public-interest researchEvidence verified through August 9, 2026
← All updates

Aqua tables Pacifico again after study reveals conditional water service

Aqua WSC confirmed that its board tabled Item 13 and did not approve proposed Resolution 26.08.02 on August 4. The open-record production shows that Garver reports existing supply and firm pumping below the capacity ratios cited in its revised study; even Pacifico's developer-supplied 14-gpm peak request depends on new Watterson wells and treatment, a pump station, storage and approximately 2.5 miles of approach main. It also contains materially different February and May layouts: the superseded concept shows two large data-center buildings and a compact power block, while the later plan shows four narrower buildings—two marked future—and a lengthened generation block. Neither provides a complete MW schedule, so 710 MW of generation and approximately 490 MW of IT load remain JETI full-buildout figures rather than capacities verified by the drawings.

Bottom line

The Board did not approve Pacifico's request—and the detailed record is more conditional than “water is feasible” suggests.

On August 4, Aqua WSC's Board voted to table Item 13, proposed Resolution 26.08.02. Aqua's own posted packet is marked DRAFT and TABLED, and its signature lines are blank. The newly obtained supporting record also shows that Garver's revised study evaluated only the developer's current 14-gpm peak request—not the full water demand of the proposed data center and power plant—and made even that limited service contingent on major capital projects.

What happened

This was the second tabling—not a denial and not an approval.

The June and August actions concern two different proposed resolutions. In June, staff required a revised data-center feasibility study. In August, the revised study returned and the Board tabled the request again. Aqua has not yet posted approved August minutes, so the official record does not yet disclose the motion maker, seconder, vote tally, stated reason or any confirmed date when the item may return.

June 3First tabling

Item 14 / Resolution 26.06.05 is tabled for a revised study.

June 22Revised study

Garver completes the capacity and hydraulic memorandum.

August 4Tabled again

Item 13 / Resolution 26.08.02 is not approved.

Current statusNo return date

Approved August minutes and any future agenda remain pending.

An independent attendee separately reported that a tabling motion was made, seconded and passed by majority after residents asked for more time. Those procedural details remain attendee-reported until Aqua publishes approved minutes. Read the attendee account ↗

What the study actually finds

Aqua cannot serve even this limited request from the existing system as-is.

Garver's existing-system table reports supply and firm pumping below the capacity ratios the study cites as TCEQ requirements. Adding Pacifico's requested service barely changes the existing shortfall, which means Pacifico did not create it. But Aqua would be making another service commitment before the public record shows when every prerequisite will be operating.

Garver revised-study Table 4-2: existing system and Pacifico's 23-LUE request
MeasureStudy benchmarkExistingWith Pacifico
Supply0.60 gpm / connection0.390.39
Firm pumping1.00 gpm / connection0.320.31
Total storage200 gal / connection254246
Elevated storage100 gal / connection108104

The study says supply and pumping are below TCEQ requirements. The packet does not discuss waivers, alternative criteria or any other regulatory basis that might change that conclusion.

Service is contingent on

Four major pieces of infrastructure

  1. New supplyAt least 3,000 gpm of Watterson wells and corresponding treatment.
  2. New pumpingA Watterson station with three new 6,000-gpm pumps.
  3. New storageOne new one-million-gallon ground-storage tank.
  4. New connection13,340 feet—about 2.53 miles—of approach main.
No complete public delivery schedule

Public records show Watterson groundwater permits advanced in 2023, completion deadlines were extended in 2024 and Aqua awarded drilling of Watterson 1 and 2 in April 2025. They do not establish that the wells are producing or supply a common in-service date for treatment, the pump station, storage tank and approach main.

The central limitation

The revised study models Pacifico's request. It does not calculate the campus's water demand.

Garver evaluates 23 living-unit equivalents, 9 gpm maximum-day demand and 14 gpm peak-hour demand supplied by the developer. It does not provide a full-campus water balance for data-center cooling, power-plant operations, turbine washing, construction, fire-water replenishment, drought conditions, wastewater or phased buildout.

23
living-unit equivalents requested
14 gpm
modeled peak-hour demand
0
fire flow in Aqua's model
2,841
acres listed in the Aqua application
What this supports

Conditional hydraulic feasibility for one narrowly defined Aqua connection after specified improvements.

What it does not support

Present capacity, a verified full-campus demand, or overall water feasibility for the data center and power plant.

Two layouts in Aqua's records

The project was materially redesigned between February and May.

Aqua's open-record production contains two genuinely different concept plans. The earlier February sheet appears in a 23-page file explicitly titled Superseded Feasibility Study. A later May Kimley-Horn sheet appears in the revised 19-page production. The building geometry, power-generation arrangement and accompanying water assumptions all changed. Neither sheet is a final approved construction plan.

Earlier / supersededFebruary 5, 2026
February 2026 superseded Pacifico concept plan showing two large data-center buildings above a compact power-generation block
Earlier Pacifico / DataPoint concept. Two 1,200-by-360-foot data-center buildings sit above a compact power block. The sheet labels temporary 16.5 MW combustion turbines, 76.4 MW combustion turbines, BESS, a substation, chillers, ammonia storage, water tanks and a proposed pond. Source: February 5 concept plan, p. 3 of Aqua's 23-page superseded production. Click to enlarge.
Later / revised recordMay 2026
May 2026 conceptual Cedar Creek layout showing four data-center buildings above a lengthened north-south power-generation block
Later Kimley-Horn concept. Four narrower data-center buildings and four chiller yards sit above a much longer power block with repeated turbine areas, two BESS areas, a substation, ORC, tanks and detention. Buildings and Chiller Yards 3 and 4 are marked “Future.” Source: May 2026, p. 7 of Aqua's revised 19-page production. Click to enlarge.

The February sheet is stamped “CONFIDENTIAL,” “Issued for Client Review” and “Not for reproduction or copying by general public.” Those markings are preserved in the image released through Aqua's open-records response. The May sheet is also expressly conceptual and says it was prepared without a final survey, topography, utility information or governmental coordination.

What changed between the superseded and revised records
FeatureEarlier recordLater record
Plan date and statusFebruary 5 client-review concept in a packet titled “Superseded”May conceptual master plan in the revised production
Data-center arrangementTwo buildings, each labeled 1,200 × 360 feetFour buildings, each approximately 1,449 × 234 feet; Buildings 3 and 4 are marked future
Power-generation arrangementCompact east-west block with 16.5 MW temporary and 76.4 MW turbine labelsLonger north-south block with repeated turbine areas, BESS, ORC and substation, but no unit ratings
Water modeled in accompanying study75 LUEs; 30 gpm maximum day; 45 gpm peak hour; plus a 250 gpm fire-tank fill rate for 16 hours23 LUEs; 9 gpm maximum day; 14 gpm peak hour; zero Aqua fire flow
Hydraulic consequenceExisting infrastructure could not maintain required pressure during fire-tank filling; the study required the approach main, two additional trunk-main segments, Watterson facilities and a 1.5-million-gallon elevated tankThe reduced request works hydraulically with the approach main, but service remains contingent on Watterson wells and treatment, pumping and a one-million-gallon ground tank because existing capacity ratios remain deficient

The application fields and engineering calculations do not use the same peak-hour numbers: the earlier application lists 35 gpm while Garver models 45; the revised application lists 12 gpm while Garver models 14. The comparison above uses the engineer's modeled values.

What the change means

The later drawing is a redesign—not proof that the earlier plan was merely Phase 1.

The strongest reading is that the May sheet replaced the February concept for the currently drawn development core. Within the May plan itself, Buildings 1 and 2 appear to form an initial stage and Buildings 3 and 4 a later stage. But neither plan supplies a formal phase schedule, turbine schedule or MW allocation, and neither is a complete master plan for all 2,841 acres.

The accompanying water request also shrank sharply: 75 to 23 LUEs and 45 to 14 gpm peak-hour demand, while the 250 gpm fire-tank refill scenario disappeared from Aqua's model. The revised study is therefore a materially narrower feasibility test—not evidence that Aqua solved the earlier, higher-demand scenario.

The May plan in detail

The later concept shows a coordinated, phased development core.

Its drawing path identifies “BLACKCHAMBER DC BASTROP,” while the sheet name combines “CEDAR CREEK DC & PG.” Separate fences and controlled entrances suggest distinct operations; shared roads, drainage and coordinated geometry show integrated physical planning. That does not, by itself, establish common legal ownership.

Data-center detail showing Buildings 1 and 2, Future Buildings 3 and 4, four chiller yards, septic fields and detention
Data-center detail. Buildings 1 and 2 are not marked future; Buildings 3 and 4 and Chiller Yards 3 and 4 are. Typical building dimensions are 1,449 by 234 feet—about 339,000 square feet each and roughly 1.36 million square feet across four footprints. The sheet also shows four 30,000-square-foot septic spray fields and a large detention area. It does not allocate the reported 490 MW IT load by building or identify cooling technology.
Power-generation detail showing turbine areas, battery storage, substation, ORC, chillers, tanks and detention
Power-generation detail. The plan depicts repeated turbine areas, two fenced BESS areas, BESS metering, a substation, an ORC area, two 520-by-320-foot chiller areas, water/fire/turbine- wash tanks, administration and control space, laydown and detention. We count 32 apparent repeated turbine positions, but the sheet has no equipment schedule, unit ratings, BESS capacity or total MW.

The detailed figures above reproduce only the May sheet. They help read that later concept; they are not final construction drawings.

How much land is currently drawn?

The clearest published footprint is about 16.8% of the stated acreage.

The plan itself does not give a total developed-acreage figure. The strongest cross-check is the two active construction-stormwater records already identified for the shared B&W Ranch site: 304 acres for Black Chamber's data-center footprint and 173.54 acres for Pacifico's power footprint. Together they total 477.54 acres.

477.54 acres
currently identified disturbance footprints
16.8%
of the 2,841-acre Aqua application figure
83.2%
outside those two filed footprints

This does not mean the remaining land will stay open or undisturbed. It may serve as buffer, future expansion, infrastructure or another use. The May drawing is a concept for the present development core—not an ultimate land-use plan for every acre.

Do the drawings show the full 710 MW and 490 MW?

They are consistent with the filed scale, but they do not prove it.

Pacifico's JETI application and Supplement 1 identify 710 MW of site-rated generation and approximately 490 MW of associated IT load as full-buildout figures. The February sheet labels 16.5 MW temporary and 76.4 MW turbine classes, while the May sheet omits unit ratings. Neither supplies a complete MW schedule, turbine models, electrical one-line or building load allocation. The May generation block may be the full current concept and its four data-center buildings may collectively represent the stated IT load, but those remain interpretations until an equipment and load schedule is published.

JETI full buildout710 MW

Site-rated generation stated in the incentive filing.

JETI full buildout~490 MW

Associated IT load stated in the incentive filing.

Both layoutsNo complete MW schedule

Visible equipment classes and geometry do not verify total capacity.

What remains unresolved

The detailed packet answers the layout question—and sharpens several others.

Water

No all-source campus balance

Cooling, construction, turbine washing, annual use, drought and phased demand are not reconciled.

Fire

No replacement fire-water design

The application removes Aqua fire flow in favor of an onsite pond, while the plan labels tanks and detention without documenting emergency reserve or refill.

Cost and timing

No complete CIP delivery plan

The packet does not give a common in-service date, current completion status or a clear split between Aqua and developer costs.

Floodplain

The records do not align on their face

Aqua's letter says no part of the property is in a special flood-hazard area, while the supporting plan depicts 100- and 500-year floodplain boundaries. The parcel and panel scope need reconciliation.

Next public action · Monday, August 10 · 9:00 a.m.

Countywide industrial-development resolution goes before Commissioners Court.

Agenda Item E.4 would declare limits on county development authority, identify water, air, habitat, noise, light and stormwater risks from unregulated large-scale industrial projects, and ask the Legislature and Governor Abbott to give Texas counties stronger authority. It is relevant to the data-center debate, but it is not a Pacifico-specific approval, abatement vote or moratorium.

Speak on Item E.4Ask for authority—and use today's tools now.

Support a strong request for real county authority. Also ask the Court to use the discretion it already has: no tax abatement or Chapter 381 agreement for a large industrial project without full-buildout disclosure, cumulative-impact review, public records and enforceable protections.

Public-participation form ↗

Mark specific agenda item E.4 / Item 4 on the form and submit it to the County Clerk before the item begins. Posted rules allow three minutes per speaker and cap total comment on an item; arriving before 9:00 a.m. with the form completed is prudent.

See every current action and meeting

Core sources and document note

Aqua's public website currently posts a 12-page packet that confirms the August 4 tabling. The February overview comes from page 3 of a separate 23-page Aqua production labeled “Superseded Feasibility Study.” The May overview and two detailed crops come from page 7 of a revised 19-page production. Aqua supplied both files through an open-records response. Plan measurements and the count of apparent turbine positions are labeled interpretations, not developer-certified equipment quantities.